Valve to valve hydrostatic testing is a specialised method of pressure testing pipelines and piping systems, where sections of the system are isolated between two valves and subjected to hydrostatic pressure individually. This approach helps identify leaks, defects, or weaknesses in localised areas of the piping network.
Conducting hydrostatic testing on a valve to valve basis offers several advantages compared to testing the complete system as a single unit. It allows for focused testing of specific sections, minimising the potential impact of a failure during testing. Additionally, valve to valve testing often requires a smaller volume of test medium, reducing costs and logistical challenges.
We perform hydrostatic and rising mains pressure testing services regularly for clients nationwide. If you’re looking for a cost-effective testing solution for water infrastructure and pipelines, don’t hesitate to get in touch.
Contact Us
When to Use Valve to Valve Testing
Valve to valve hydrostatic testing is particularly beneficial in the following scenarios:
For extensive piping networks with multiple branches, loops, or interconnections, testing the entire system at once may be impractical or challenging. Valve to valve testing enables a more manageable and targeted approach.
Piping systems with numerous branches or loops can benefit from valve to valve testing. Isolating individual sections can simplify the testing process, facilitating more accurate identification of potential issues.
Valve to valve testing allows for specific sections to be evaluated, especially when existing piping systems undergo repairs, replacements, or modifications.
Step-by-Step Valve to Valve Testing Procedure
System Preparation
Identify the section of the piping system to be tested and isolate it between two valves by closing off the appropriate isolation valves.
Install temporary blanks or blinds at the valve locations to provide a physical barrier and ensure complete isolation of the test section.
Install the necessary connections, fittings, and adapters to enable the attachment of test equipment, such as pumps, pressure gauges, and vents.
Filling and Venting
Fill the isolated section with the chosen test medium, typically water or another suitable liquid approved for hydrostatic testing.
Properly vent the section to remove any trapped air pockets, ensuring that the test medium completely fills the isolated segment.
Pressurisation
Connect the pressurisation equipment, such as high-pressure pumps or compressors, and gradually increase the pressure within the isolated section to the specified test pressure.
Closely monitor the pressure gauges and visually inspect the section for any signs of leaks or pressure drops during the pressurisation process.
Hold Period
Once the desired test pressure is achieved, maintain it within the specified tolerance range for a predetermined hold period, typically ranging from several hours to a full day or more, depending on the specific testing requirements.
Throughout the hold period, continuously monitor the pressure gauges and perform visual inspections to detect any pressure changes or visible leaks.
Depressurisation and Draining
After successfully completing the hold period, safely release the pressure from the tested section following proper depressurisation procedures.
Drain the test medium from the isolated section, preparing it for the next valve to valve section to be tested, if applicable.
Documentation
- Recording Test Data and Results: Thoroughly document all test data, observations, and results for the valve to valve section tested, including pressure readings, hold times, and any deviations or anomalies detected during the testing process.
Testing Requirements and Standards
Valve to valve hydrostatic testing must comply with relevant industry standards and regulations to ensure safety and consistency. We adhere to these standards meticulously. Key UK guidelines include:
- BS 806 and BS 1306: These British Standards provide comprehensive requirements for the design, construction, and operation of ferrous piping systems, including hydrostatic testing procedures and acceptance criteria.
- BS EN 14161 and BS EN 1594: These European standards, implemented in the UK as British Normative Standards, cover pressure testing of liquid petroleum pipelines using water as the test medium.
- Pipelines Safety Regulations 1996 (PSR): The PSR regulations govern the testing and operation of pipelines transporting hazardous materials, including specific requirements for hydrostatic testing.
These standards and regulations define factors such as test pressures, hold durations, test medium selection, and acceptance criteria based on the piping material, design pressure, and intended service.
Safety Considerations
Hydrostatic testing, especially valve to valve testing, involves working with high pressures and potentially hazardous materials. Safety must be the top priority throughout the testing process. Critical safety considerations include:
- High-Pressure Hazards: The pressures involved in hydrostatic testing can be extremely high, posing risks of equipment failure, piping ruptures, and injuries. Strict adherence to safety protocols, proper use of personal protective equipment (PPE), and maintaining safe distances are essential.
- Water Discharge and Environmental Concerns: The discharge of test medium (water or other fluids) can potentially impact the surrounding environment. Proper containment, treatment, and disposal methods should be implemented to mitigate environmental risks.
- Emergency Response Plans: Comprehensive emergency response plans should be in place to address potential incidents, such as leaks, piping failures, or other unforeseen events during testing. These plans should include procedures for isolating affected areas, mitigating risks, and ensuring the safety of personnel and the environment.
Advantages of Valve to Valve Testing
Valve to valve testing allows for focused evaluation of specific sections, enabling more efficient identification and isolation of potential issues.
By testing smaller isolated sections, the required volume of test medium (e.g., water) is significantly reduced, minimising costs and logistical challenges.
In the event of a failure during testing, the impact is contained within the isolated section, reducing potential risks and consequences.
Limitations of Valve to Valve Testing
Testing each section individually can be more time-consuming compared to testing the complete system at once.
Valve to valve testing requires the installation of temporary blanks, blinds, and connections for test equipment, adding complexity and preparation time.
While effective for localised testing, valve to valve testing may not fully replicate the stress conditions experienced by the complete system during operation, potentially missing interactions between different sections.